At 1:45 PM -0500 11/2/98, Pablo Hopman wrote: >So the 3 columns that I would like to be filled in: > > i. # tested by Nov 17 - the number of chips tested and ready to be sent > off by Nov 17th > ii. The date that 1/2 of all chips needed ( ie for 80 hybrids) will be > tested and ready > iii. The date that all chips needed (ie for 160 hybrids) will be > tested and ready > > > # tested by 11/17 Date 1/2 Date all >---------------------------------------------------------------------------- >SVX 413 11/25(640chips) 12/18(1280ch) Assumptions: 77% yield, 1.5 wafers (54 chips) tested per day, 5 days/week, and OSU doesn't need any more good (0,1 bad ch) chips beyond the approx 86 I have already sent. We get the probe station back next Monday and I have assumed the only break is for Thanksgiving, i.e. no equip failures. HOWEVER, the most radical assumption is delivering 1280 chips, since we have only 44 wafers and 86 good chips have already gone to OSU! Given the above conditions the total deliverable will only be 44*36*0.77-86 = 1133, or enough for 141 hybrids. -George